The present application was filed under Section 33 of the Insolvency and Bankruptcy Code, 2016 (IBC) by Mr. Neehal Mahamulal Pathan, the Resolution Professional (RP) of M/s. KCG Engineers Private Limited (Corporate Debtor), seeking an order for liquidation. The Corporate Insolvency Resolution Process (CIRP) for KCG Engineers Private Limited commenced on January 20, 2020, following a Section 9 petition filed by Mr. Siddesh Kosabe, Proprietor of Ammu Enterprises (Operational Creditor). Mr. Neehal Mahamulal Pathan was appointed as the Interim Resolution Professional (IRP). The initial CIRP period expired on July 18, 2020, and even after permitted extensions, the CIRP remained valid only until July 31, 2021. Despite this, the CIRP continued for an additional 1295 days
…The present application has been filed under Section 33 of the Insolvency and Bankruptcy Code, 2016 by the Resolution Professional of M/s. KCG Engineers Private Limited (Corporate Debtor) seeking liquidation.
The Company Petition No. CP(IB)/4346/MB/2019 was filed under Section 9 of the IBC by Mr. Siddesh Kosabe, Proprietor of Ammu Enterprises, as the Operational Creditor.
The Adjudicating Authority admitted the petition into Corporate Insolvency Resolution Process (CIRP) vide Order dated 20.01.2020, and Mr. Neehal Mahamulal Pathan was appointed as the Interim Resolution Professional (IRP).
The Applicant made a public announcement in Form A on 31.01.2020 and published Form G for Expression of Interest on 04.03.2021.
The initial CIRP period of 180 days expired on 18.07.2020.
…Sign in to view the parties.
Company Petition No. CP(IB)/4346/MB/2019…
Public announc…
The present application was filed under Section 33 of the Insolvency and Bankruptcy Code, 2016 (IBC) by Mr. Neehal Mahamulal Pathan, the Resolution Professional (RP) of M/s. KCG Engineers Private Limited (Corporate Debtor), seeking an order for liquidation. The Corporate Insolvency Resolution Process (CIRP) for KCG Engineers Private Limited commenced on January 20, 2020, following a Section 9 petition filed by Mr. Siddesh Kosabe, Proprietor of Ammu Enterprises (Operational Creditor). Mr. Neehal Mahamulal Pathan was appointed as the Interim Resolution Professional (IRP). The initial CIRP period expired on July 18, 2020, and even after permitted extensions, the CIRP remained valid only until July 31, 2021. Despite this, the CIRP continued for an additional 1295 days
…The present application has been filed under Section 33 of the Insolvency and Bankruptcy Code, 2016 by the Resolution Professional of M/s. KCG Engineers Private Limited (Corporate Debtor) seeking liquidation.
The Company Petition No. CP(IB)/4346/MB/2019 was filed under Section 9 of the IBC by Mr. Siddesh Kosabe, Proprietor of Ammu Enterprises, as the Operational Creditor.
The Adjudicating Authority admitted the petition into Corporate Insolvency Resolution Process (CIRP) vide Order dated 20.01.2020, and Mr. Neehal Mahamulal Pathan was appointed as the Interim Resolution Professional (IRP).
The Applicant made a public announcement in Form A on 31.01.2020 and published Form G for Expression of Interest on 04.03.2021.
The initial CIRP period of 180 days expired on 18.07.2020.