An application was filed seeking exclusion of 34 days from the CIRP period, allowing an application under Section 12A of the IBC, relieving Indus Projects Limited from CIRP, and terminating the CIRP of the Corporate Debtor, discharging the IRP.
The application seeks exclusion of 34 days from the CIRP period of the Corporate Debtor.
The application seeks to allow the present application under Section 12A of the Insolvency and Bankruptcy Code, 2016.
The application seeks to relieve M/s Indus Projects Limited from the rigours of Corporate Insolvency Resolution Process (CIRP).
The application seeks to terminate the CIRP of the Corporate Debtor and discharge the IRP.
The Corporate Debtor was admitted to CIRP vide an order dated 08.05.2025.
The IRP received form-FA from the Applicant Operational Creditor on 16.06.2025.
The RP affirmed the present Application on 19.06.2025.
No Committee of Creditors (CoC) has been formed in the matter so far.
…Sign in to view the parties.
Company Petition…
Admission Order dated…
An application was filed seeking exclusion of 34 days from the CIRP period, allowing an application under Section 12A of the IBC, relieving Indus Projects Limited from CIRP, and terminating the CIRP of the Corporate Debtor, discharging the IRP.
The application seeks exclusion of 34 days from the CIRP period of the Corporate Debtor.
The application seeks to allow the present application under Section 12A of the Insolvency and Bankruptcy Code, 2016.
The application seeks to relieve M/s Indus Projects Limited from the rigours of Corporate Insolvency Resolution Process (CIRP).
The application seeks to terminate the CIRP of the Corporate Debtor and discharge the IRP.
The Corporate Debtor was admitted to CIRP vide an order dated 08.05.2025.
The IRP received form-FA from the Applicant Operational Creditor on 16.06.2025.
The RP affirmed the present Application on 19.06.2025.
No Committee of Creditors (CoC) has been formed in the matter so far.
…Company Petition…
Admission Order dated…