The Employees' Provident Fund Organization (EPFO) filed an application seeking the admission and priority payment of provident fund dues, including interest and damages, amounting to Rs.2,15,69,819/- from M/s Greater Kailash Hospitals Pvt. Ltd. (Corporate Debtor), which is undergoing CIRP. The EPFO argued that these dues are statutory, constitute a first charge on the Corporate Debtor's assets, and are excluded from the liquidation estate under the IBC. The Resolution Professional (RP), Chhaya Gupta, contended that the claims, particularly damages under Section 14B, were not fully admissible, required reconciliation with audited records, and could not be determined during the moratorium period. An erstwhile IRP had admitted a claim of Rs.67,05,609/- for collation,
…The Applicant, Employees' Provident Fund Organization (EPFO), filed Interlocutory Application No. 448 of 2025 under Section 60(5) of the IBC read with Rule 11 of the NCLT Rules.
M/s Greater Kailash Hospitals Pvt. Ltd. ("Corporate Debtor") is an establishment registered under the Employees' Provident Funds and Miscellaneous Provisions Act, 1952.
The Corporate Debtor was admitted into Corporate Insolvency Resolution Process ("CIRP") on 30.07.2024 by an Order passed in CP(IB)/03/2024.
Mr. Mangesh Vitthal Kekre was appointed as the Interim Resolution Professional ("IRP") for the Corporate Debtor.
A moratorium under Section 14 of the IBC came into effect from 30.07.2024.
The last date for submission of claims in the CIRP was 15.08.2024.
…Sign in to view the parties.
The Corporate Debtor, M/s Greater Kailash…
The last date for submission of claims in…
The Employees' Provident Fund Organization (EPFO) filed an application seeking the admission and priority payment of provident fund dues, including interest and damages, amounting to Rs.2,15,69,819/- from M/s Greater Kailash Hospitals Pvt. Ltd. (Corporate Debtor), which is undergoing CIRP. The EPFO argued that these dues are statutory, constitute a first charge on the Corporate Debtor's assets, and are excluded from the liquidation estate under the IBC. The Resolution Professional (RP), Chhaya Gupta, contended that the claims, particularly damages under Section 14B, were not fully admissible, required reconciliation with audited records, and could not be determined during the moratorium period. An erstwhile IRP had admitted a claim of Rs.67,05,609/- for collation,
…The Applicant, Employees' Provident Fund Organization (EPFO), filed Interlocutory Application No. 448 of 2025 under Section 60(5) of the IBC read with Rule 11 of the NCLT Rules.
M/s Greater Kailash Hospitals Pvt. Ltd. ("Corporate Debtor") is an establishment registered under the Employees' Provident Funds and Miscellaneous Provisions Act, 1952.
The Corporate Debtor was admitted into Corporate Insolvency Resolution Process ("CIRP") on 30.07.2024 by an Order passed in CP(IB)/03/2024.
Mr. Mangesh Vitthal Kekre was appointed as the Interim Resolution Professional ("IRP") for the Corporate Debtor.
A moratorium under Section 14 of the IBC came into effect from 30.07.2024.
The last date for submission of claims in the CIRP was 15.08.2024.
…The Corporate Debtor, M/s Greater Kailash…
The last date for submission of claims in…