The case pertains to an application filed by Mr. Sudip Bhattacharya, the Resolution Professional (RP) of the Corporate Debtor, Reliance Naval & Engineering Limited, under Section 30(6) read with Section 31 of the Insolvency and Bankruptcy Code (IBC), 2016, for the approval of the Resolution Plan. The Corporate Debtor was admitted into the Corporate Insolvency Resolution Process (CIRP) on 15.01.2020, following an application by the financial creditor, IDBI Bank Limited, under Section 7 of the IBC. Initially, Mr. Rajeev Bal Sawangikar was appointed as the Interim Resolution Professional (IRP), who was later replaced by the current RP. The RP constituted a Committee of Creditors (CoC) comprising 22 financial creditors. The CoC approved the eligibility criteria for
…The Corporate Debtor, Reliance Naval & Engineering Limited, underwent Corporate Insolvency Resolution Process (CIRP) initiated by IDBI Bank Limited under Section 7 of the Insolvency and Bankruptcy Code (IBC), 2016. Mr. Sudip Bhattacharya served as the Resolution Professional (RP), replacing the initial Interim Resolution Professional (IRP). A Committee of Creditors (CoC) was formed, comprising 22 financial creditors. The CoC invited prospective resolution applicants to submit Expressions of Interest (EoIs). Three EoIs were received from Jindal Steel and Power Limited, Hazel Mercantile Limited (along with its strategic investor Swan Energy Ltd.), and Global Marketing System DMCC. The CoC approved the resolution plan of Hazel Mercantile Limited with 94.86% voting
…Sign in to view the parties.
Corporate Debtor admitted into Corporate…
2nd Committ…
Sign in to view related legal provisions.
The case pertains to an application filed by Mr. Sudip Bhattacharya, the Resolution Professional (RP) of the Corporate Debtor, Reliance Naval & Engineering Limited, under Section 30(6) read with Section 31 of the Insolvency and Bankruptcy Code (IBC), 2016, for the approval of the Resolution Plan. The Corporate Debtor was admitted into the Corporate Insolvency Resolution Process (CIRP) on 15.01.2020, following an application by the financial creditor, IDBI Bank Limited, under Section 7 of the IBC. Initially, Mr. Rajeev Bal Sawangikar was appointed as the Interim Resolution Professional (IRP), who was later replaced by the current RP. The RP constituted a Committee of Creditors (CoC) comprising 22 financial creditors. The CoC approved the eligibility criteria for
…The Corporate Debtor, Reliance Naval & Engineering Limited, underwent Corporate Insolvency Resolution Process (CIRP) initiated by IDBI Bank Limited under Section 7 of the Insolvency and Bankruptcy Code (IBC), 2016. Mr. Sudip Bhattacharya served as the Resolution Professional (RP), replacing the initial Interim Resolution Professional (IRP). A Committee of Creditors (CoC) was formed, comprising 22 financial creditors. The CoC invited prospective resolution applicants to submit Expressions of Interest (EoIs). Three EoIs were received from Jindal Steel and Power Limited, Hazel Mercantile Limited (along with its strategic investor Swan Energy Ltd.), and Global Marketing System DMCC. The CoC approved the resolution plan of Hazel Mercantile Limited with 94.86% voting
…Corporate Debtor admitted into Corporate…
2nd Committ…
Sign in to view related legal provisions.