In IA No. 156/2022, INOX WIND LTD. filed an application under Section 60(5) of the Insolvency and Bankruptcy Code, 2016, seeking the release of remaining materials (loosed materials like plates, flanges, internal parts, fasteners, frames, clamps, segments, and ladders) laying in the Jambusar Bharuch plant of the Corporate Debtor, valued at Rs. 1,36,00,000/-, and to reconcile the accounts for the rest of the raw MS plates laying in the Bharuch factory, worth around Rs. 5,77,00,000/-. INOX WIND LTD. had been placing orders with the Corporate Debtor since 2016 for fabrication of towers and other equipment, providing the raw material. The Corporate Debtor entered the CIR Process on August 14, 2019. The Resolution Plan was approved on October 6, 2021, and the Successful
…INOX WIND LTD. (Applicant) filed an application seeking the release of certain materials (plates, flanges, internal parts, fasteners, frames, clamps, segments, and ladders) laying in the Jambusar Bharuch plant of FEDDERS ELECTRIC & ENGINEERING LTD. (Corporate Debtor). The materials were valued at Rs. 1,36,00,000/-. INOX WIND LTD. also sought reconciliation of accounts for raw MS plates worth Rs. 5,77,00,000/-. INOX WIND LTD. had been placing orders with the Corporate Debtor since 2016 for the fabrication of towers and other equipment, providing the raw material. The Corporate Debtor entered the CIR Process on August 14, 2019. A Resolution Plan was approved on October 6, 2021, and the Successful Resolution Applicant took over control on February 21, 2022. INOX WIND
…Sign in to view the parties.
INOX WIND LTD. started placing orders with the…
Date of the last…
In IA No. 156/2022, INOX WIND LTD. filed an application under Section 60(5) of the Insolvency and Bankruptcy Code, 2016, seeking the release of remaining materials (loosed materials like plates, flanges, internal parts, fasteners, frames, clamps, segments, and ladders) laying in the Jambusar Bharuch plant of the Corporate Debtor, valued at Rs. 1,36,00,000/-, and to reconcile the accounts for the rest of the raw MS plates laying in the Bharuch factory, worth around Rs. 5,77,00,000/-. INOX WIND LTD. had been placing orders with the Corporate Debtor since 2016 for fabrication of towers and other equipment, providing the raw material. The Corporate Debtor entered the CIR Process on August 14, 2019. The Resolution Plan was approved on October 6, 2021, and the Successful
…INOX WIND LTD. (Applicant) filed an application seeking the release of certain materials (plates, flanges, internal parts, fasteners, frames, clamps, segments, and ladders) laying in the Jambusar Bharuch plant of FEDDERS ELECTRIC & ENGINEERING LTD. (Corporate Debtor). The materials were valued at Rs. 1,36,00,000/-. INOX WIND LTD. also sought reconciliation of accounts for raw MS plates worth Rs. 5,77,00,000/-. INOX WIND LTD. had been placing orders with the Corporate Debtor since 2016 for the fabrication of towers and other equipment, providing the raw material. The Corporate Debtor entered the CIR Process on August 14, 2019. A Resolution Plan was approved on October 6, 2021, and the Successful Resolution Applicant took over control on February 21, 2022. INOX WIND
…INOX WIND LTD. started placing orders with the…
Date of the last…