The case involves IA(IBC) 385 & 407/2023 in CP(IB) No. 329/7/HDB/2020, initiated under Section 7 of the Insolvency and Bankruptcy Code (IBC), 2016. State Bank of India, the Financial Creditor, filed a petition against Dharti Dredging and Infrastructure Ltd, the Corporate Debtor. The Corporate Insolvency Resolution Process (CIRP) was initiated on 05.04.2022. The Resolution Professional (RP) published invitations for Expression of Interest (EoI), received multiple EOIs, and extended the submission deadline for the Resolution Plan. The Consortium of Yogayatan Ports Private Limited and Dr. Rajendra Raja Bali Singh submitted a resolution plan, which was later approved by the Committee of Creditors (CoC) with 100% voting share. Another resolution plan submitted by Mr.
…1. State Bank of India initiated CIRP against Dharti Dredging and Infrastructure Ltd under Section 7 of IBC, 2016.
2. CIRP commenced on 05.04.2022.
3. Mr. Madhusudhan Rao Gonugunta was appointed as the Resolution Professional (RP).
4. RP published invitations for Expression of Interest (EoI) and received multiple EOIs.
5. The deadline for submission of the Resolution Plan was extended to 10.10.2022.
6. Consortium of Yogayatan Ports Private Limited and Dr. Rajendra Raja Bali Singh submitted a resolution plan.
7. Another resolution plan was submitted by Mr. Akumulla Rajendra, which was rejected by the RP.
8. The CoC approved the resolution plan of Consortium of Yogayatan Ports Private Limited and Dr. Rajendra Raja Bali Singh with 100% voting share on 23.02.2023.
9. The approved
Sign in to view the parties.
Filing of the…
CIRP commenced against…
The case involves IA(IBC) 385 & 407/2023 in CP(IB) No. 329/7/HDB/2020, initiated under Section 7 of the Insolvency and Bankruptcy Code (IBC), 2016. State Bank of India, the Financial Creditor, filed a petition against Dharti Dredging and Infrastructure Ltd, the Corporate Debtor. The Corporate Insolvency Resolution Process (CIRP) was initiated on 05.04.2022. The Resolution Professional (RP) published invitations for Expression of Interest (EoI), received multiple EOIs, and extended the submission deadline for the Resolution Plan. The Consortium of Yogayatan Ports Private Limited and Dr. Rajendra Raja Bali Singh submitted a resolution plan, which was later approved by the Committee of Creditors (CoC) with 100% voting share. Another resolution plan submitted by Mr.
…1. State Bank of India initiated CIRP against Dharti Dredging and Infrastructure Ltd under Section 7 of IBC, 2016.
2. CIRP commenced on 05.04.2022.
3. Mr. Madhusudhan Rao Gonugunta was appointed as the Resolution Professional (RP).
4. RP published invitations for Expression of Interest (EoI) and received multiple EOIs.
5. The deadline for submission of the Resolution Plan was extended to 10.10.2022.
6. Consortium of Yogayatan Ports Private Limited and Dr. Rajendra Raja Bali Singh submitted a resolution plan.
7. Another resolution plan was submitted by Mr. Akumulla Rajendra, which was rejected by the RP.
8. The CoC approved the resolution plan of Consortium of Yogayatan Ports Private Limited and Dr. Rajendra Raja Bali Singh with 100% voting share on 23.02.2023.
9. The approved
Filing of the…
CIRP commenced against…