Ashish Vincom Private Limited, the Financial Creditor, filed an application under Section 7 of the Insolvency and Bankruptcy Code, 2016, seeking initiation of Corporate Insolvency Resolution Process (CIRP) against Neelkamal Grih Nirman Private Limited, the Corporate Debtor. The Financial Creditor claimed that the Corporate Debtor approached them for the sale of a flat and a covered car parking space for a total amount of Rs. 50,00,000/-. The Financial Creditor paid an advance of Rs. 5,00,000/- to the Corporate Debtor on 6th March, 2014, which was reflected in the Corporate Debtor's balance sheets as 'Advance against Property'. The Financial Creditor alleged that the Corporate Debtor defaulted on delivering the flat by 30th September, 2016, and failed to refund the
…1. Ashish Vincom Private Limited (Financial Creditor) claimed that Neelkamal Grih Nirman Private Limited (Corporate Debtor) approached them for the sale of a flat of 1600 sq ft. and one covered car parking space for a total amount of Rs. 50,00,000/- at the Corporate Debtor's proposed project site.
2. The Financial Creditor paid an advance of Rs. 5,00,000/- to the Corporate Debtor on 6th March, 2014, via bank transfer.
3. The Financial Creditor relied on a Development Agreement dated 12th May, 2013, between the Corporate Debtor and Srijan Mondal and others (landowners).
4. The Financial Creditor claimed that the Corporate Debtor assured them that the flat would be delivered by 30th September, 2016, and in case of delay, the advance amount would be refunded with 18%
Sign in to view the parties.
Development Agreement dated 12th May, 2013…
Financial Creditor paid an advance of Rs.…
Ashish Vincom Private Limited, the Financial Creditor, filed an application under Section 7 of the Insolvency and Bankruptcy Code, 2016, seeking initiation of Corporate Insolvency Resolution Process (CIRP) against Neelkamal Grih Nirman Private Limited, the Corporate Debtor. The Financial Creditor claimed that the Corporate Debtor approached them for the sale of a flat and a covered car parking space for a total amount of Rs. 50,00,000/-. The Financial Creditor paid an advance of Rs. 5,00,000/- to the Corporate Debtor on 6th March, 2014, which was reflected in the Corporate Debtor's balance sheets as 'Advance against Property'. The Financial Creditor alleged that the Corporate Debtor defaulted on delivering the flat by 30th September, 2016, and failed to refund the
…1. Ashish Vincom Private Limited (Financial Creditor) claimed that Neelkamal Grih Nirman Private Limited (Corporate Debtor) approached them for the sale of a flat of 1600 sq ft. and one covered car parking space for a total amount of Rs. 50,00,000/- at the Corporate Debtor's proposed project site.
2. The Financial Creditor paid an advance of Rs. 5,00,000/- to the Corporate Debtor on 6th March, 2014, via bank transfer.
3. The Financial Creditor relied on a Development Agreement dated 12th May, 2013, between the Corporate Debtor and Srijan Mondal and others (landowners).
4. The Financial Creditor claimed that the Corporate Debtor assured them that the flat would be delivered by 30th September, 2016, and in case of delay, the advance amount would be refunded with 18%
Development Agreement dated 12th May, 2013…