M/s Powertech Engineers (Operational Creditor/Applicant) filed an application under Section 9 of the IBC against M/s GEPDEC Infratech Limited (Corporate Debtor/Respondent) to initiate CIRP due to an unpaid operational debt of Rs. 16,68,93,304.94. The Corporate Debtor disputed the claim, asserting that the parties were joint venture partners and the transactions were internal arrangements, not operational debt.
M/s Powertech Engineers (Operational Creditor/Applicant) filed an application under Section 9 of the IBC against M/s GEPDEC Infratech Limited (Corporate Debtor/Respondent).
The application sought to initiate Corporate Insolvency Resolution Process (CIRP) against the Corporate Debtor.
The total outstanding debt claimed was Rs. 16,68,93,304.94 (Principal Amount) plus interest.
The initial date of default was 30.11.2018, with subsequent defaults until 15.09.2019.
The Operational Creditor and Corporate Debtor entered into a joint venture agreement on 17.10.2025 for the construction of a 220/33KV GIS Grid Sub-Station.
U.P. Rajkiya Nirman Limited (URNL) issued a Letter of Award dated 12.03.2016 for the said project.
…Sign in to view the parties.
U.P. Rajkiya Nirman Limited (URNL) issued a…
Corporate Debtor/Respondent and Operational…
M/s Powertech Engineers (Operational Creditor/Applicant) filed an application under Section 9 of the IBC against M/s GEPDEC Infratech Limited (Corporate Debtor/Respondent) to initiate CIRP due to an unpaid operational debt of Rs. 16,68,93,304.94. The Corporate Debtor disputed the claim, asserting that the parties were joint venture partners and the transactions were internal arrangements, not operational debt.
M/s Powertech Engineers (Operational Creditor/Applicant) filed an application under Section 9 of the IBC against M/s GEPDEC Infratech Limited (Corporate Debtor/Respondent).
The application sought to initiate Corporate Insolvency Resolution Process (CIRP) against the Corporate Debtor.
The total outstanding debt claimed was Rs. 16,68,93,304.94 (Principal Amount) plus interest.
The initial date of default was 30.11.2018, with subsequent defaults until 15.09.2019.
The Operational Creditor and Corporate Debtor entered into a joint venture agreement on 17.10.2025 for the construction of a 220/33KV GIS Grid Sub-Station.
U.P. Rajkiya Nirman Limited (URNL) issued a Letter of Award dated 12.03.2016 for the said project.
…U.P. Rajkiya Nirman Limited (URNL) issued a…
Corporate Debtor/Respondent and Operational…