An application was filed under Section 7 of the Insolvency and Bankruptcy Code (IBC), 2016, by Edelweiss Asset Reconstruction Company Limited against Takshashila Heights Private Limited.
Edelweiss Asset Reconstruction Company Limited filed an application under Section 7 of the IBC against Takshashila Heights Private Limited.
The Hon'ble Supreme Court dismissed a Civil Appeal No.10012 of 2025 filed by Takshashila Heights Private Limited against Edelweiss Asset Reconstruction Company Limited.
The application under Section 7 of the IBC was admitted, initiating the CIRP against Takshashila Heights Private Limited.
Orion Resolution & Turnaround Private Limited was appointed as the Interim Resolution Professional (IRP).
A moratorium was declared as per the provisions of Section 14 of the IBC.
The Applicant/Financial Creditor is directed to deposit a sum of Rs. 2.00 lacs with the IRP.
Sign in to view the parties.
Orion Resolution &…
Order delivered on…
An application was filed under Section 7 of the Insolvency and Bankruptcy Code (IBC), 2016, by Edelweiss Asset Reconstruction Company Limited against Takshashila Heights Private Limited.
Edelweiss Asset Reconstruction Company Limited filed an application under Section 7 of the IBC against Takshashila Heights Private Limited.
The Hon'ble Supreme Court dismissed a Civil Appeal No.10012 of 2025 filed by Takshashila Heights Private Limited against Edelweiss Asset Reconstruction Company Limited.
The application under Section 7 of the IBC was admitted, initiating the CIRP against Takshashila Heights Private Limited.
Orion Resolution & Turnaround Private Limited was appointed as the Interim Resolution Professional (IRP).
A moratorium was declared as per the provisions of Section 14 of the IBC.
The Applicant/Financial Creditor is directed to deposit a sum of Rs. 2.00 lacs with the IRP.
Orion Resolution &…
Order delivered on…