This case involves an appeal filed by Wave Megacity Centre Private Limited, a Corporate Debtor, challenging an order dated 06.06.2022 passed by the National Company Law Tribunal (NCLT), New Delhi, Principal Bench. The NCLT order allowed IA No.2026 of 2021 and IA No.2378 of 2021 filed under Section 65 of the Insolvency and Bankruptcy Code, 2016 (IBC), and dismissed Company Petition No. (IB) No.197(PB)/2021 filed by the Appellant under Section 10 of the IBC. The case arises from a lease deed between Noida Authority and Wave Megacity Ltd. where Wave Megacity failed to complete construction and repay the premium amount. Homebuyers filed applications under Section 65 alleging fraudulent intent in filing the Section 10 application.
Wave Megacity Centre Private Limited, the Corporate Debtor, entered into a lease deed with Noida Authority on 02.09.2011 for land in Sectors 25A and 32, NOIDA. Wave Megacity paid 10% of the total consideration (Rs.662.29 Crores) but failed to pay the remaining 90% and complete construction. The Appellant launched residential and commercial projects, promising possession by 2016, but failed to deliver despite receiving 90% consideration from homebuyers. The State Government announced the Project Settlement Policy (PSP) in 2016, under which Wave Megacity surrendered a portion of the land. Noida Authority demanded payment of Rs.2717,53,65,192/- in 2020, which Wave Megacity challenged. The Corporate Debtor filed an application under Section 10 of the IBC on 25.03.2021,
…Sign in to view the parties.
Lease Deed signed…
State Government of…
This case involves an appeal filed by Wave Megacity Centre Private Limited, a Corporate Debtor, challenging an order dated 06.06.2022 passed by the National Company Law Tribunal (NCLT), New Delhi, Principal Bench. The NCLT order allowed IA No.2026 of 2021 and IA No.2378 of 2021 filed under Section 65 of the Insolvency and Bankruptcy Code, 2016 (IBC), and dismissed Company Petition No. (IB) No.197(PB)/2021 filed by the Appellant under Section 10 of the IBC. The case arises from a lease deed between Noida Authority and Wave Megacity Ltd. where Wave Megacity failed to complete construction and repay the premium amount. Homebuyers filed applications under Section 65 alleging fraudulent intent in filing the Section 10 application.
Wave Megacity Centre Private Limited, the Corporate Debtor, entered into a lease deed with Noida Authority on 02.09.2011 for land in Sectors 25A and 32, NOIDA. Wave Megacity paid 10% of the total consideration (Rs.662.29 Crores) but failed to pay the remaining 90% and complete construction. The Appellant launched residential and commercial projects, promising possession by 2016, but failed to deliver despite receiving 90% consideration from homebuyers. The State Government announced the Project Settlement Policy (PSP) in 2016, under which Wave Megacity surrendered a portion of the land. Noida Authority demanded payment of Rs.2717,53,65,192/- in 2020, which Wave Megacity challenged. The Corporate Debtor filed an application under Section 10 of the IBC on 25.03.2021,
…Lease Deed signed…
State Government of…