Rakesh Dalpatram Panchal, Ex-Director of M/s Gemini Engi. Fab. Private Limited (Corporate Debtor), filed an appeal against the NCLT's order dated 24.03.2025, which admitted a Section 9 application filed by M/s. Kisaan Steels Pvt. Ltd. (Operational Creditor). The appellant contended that there were pre-existing disputes regarding the quality of goods and delivery delays, and that an email relied upon by the NCLT was misinterpreted as an admission of liability, being conditional upon account reconciliation.
Rakesh Dalpatram Panchal, Ex-Director of M/s Gemini Engi. Fab. Private Limited (Corporate Debtor), filed an appeal against the NCLT order dated 24.03.2025.
The NCLT order admitted a Section 9 application filed by Respondent No.1 (M/s. Kisaan Steels Pvt. Ltd.) against the Corporate Debtor.
The Corporate Debtor and Respondent No.1 entered into several purchase orders between December 2021 and June 2022 for the supply of forgings and other materials.
The Appellant claimed that Respondent No.1 failed to adhere to delivery timelines and supplied defective goods, leading to multiple disputes.
The Appellant claimed to have imposed penalties on Respondent No.1 for its breaches, and account reconciliation was ongoing.
…Sign in to view the parties.
Respondent No. 1…
Corporate Debtor and Respondent No.1 entered…
Rakesh Dalpatram Panchal, Ex-Director of M/s Gemini Engi. Fab. Private Limited (Corporate Debtor), filed an appeal against the NCLT's order dated 24.03.2025, which admitted a Section 9 application filed by M/s. Kisaan Steels Pvt. Ltd. (Operational Creditor). The appellant contended that there were pre-existing disputes regarding the quality of goods and delivery delays, and that an email relied upon by the NCLT was misinterpreted as an admission of liability, being conditional upon account reconciliation.
Rakesh Dalpatram Panchal, Ex-Director of M/s Gemini Engi. Fab. Private Limited (Corporate Debtor), filed an appeal against the NCLT order dated 24.03.2025.
The NCLT order admitted a Section 9 application filed by Respondent No.1 (M/s. Kisaan Steels Pvt. Ltd.) against the Corporate Debtor.
The Corporate Debtor and Respondent No.1 entered into several purchase orders between December 2021 and June 2022 for the supply of forgings and other materials.
The Appellant claimed that Respondent No.1 failed to adhere to delivery timelines and supplied defective goods, leading to multiple disputes.
The Appellant claimed to have imposed penalties on Respondent No.1 for its breaches, and account reconciliation was ongoing.
…Respondent No. 1…
Corporate Debtor and Respondent No.1 entered…