This case involves an appeal against an order dated 25.07.2023 by the National Company Law Tribunal (NCLT), Mumbai Bench – IV, which admitted a Section 7 application filed by Respondents No. 1 to 3. The appellant, the suspended director of the Corporate Debtor, Atul Projects India Private Limited, challenged the order. The dispute arises from a Memorandum of Understanding (MoU) and subsequent agreements (AoU, AoA) related to a real estate redevelopment project in Mumbai. The project involved the Corporate Debtor, Thakkars (partners), and Investors (Respondents 1-3). The Investors provided funds for the project, but due to disputes and lack of progress, the project stalled. The core issue revolves around the repayment of the investment and whether the Section 7
…In 2010, Atul Projects India Private Limited (Corporate Debtor) planned a redevelopment project in Mumbai. A Memorandum of Understanding (MoU) was signed on 2010-05-16 with the Owners, Confirming Parties, and the Corporate Debtor. The Corporate Debtor was to pay ₹9.40 Crores to the Owners. Thakkars (Deepak Vinod Thakkar and Prashant Vinod Thakkar) entered into an Articles of Understanding (AoU) with the Corporate Debtor, agreeing to jointly redevelop the project. The Thakkars were to get an investment of ₹6 Crores. An Articles of Agreement (AoA) was signed on 2010-05-16 between the Thakkars and Manish Pardasani, Savinder Singh Lamba, and Kulbir Singh Rekhi (Respondents No. 1 to 3), the Investors. The Investors would provide ₹6 Crores to the Thakkars, and in return,
…Sign in to view the parties.
Memorandum of Understanding (MoU), Articles…
The Corporate Debtor…
This case involves an appeal against an order dated 25.07.2023 by the National Company Law Tribunal (NCLT), Mumbai Bench – IV, which admitted a Section 7 application filed by Respondents No. 1 to 3. The appellant, the suspended director of the Corporate Debtor, Atul Projects India Private Limited, challenged the order. The dispute arises from a Memorandum of Understanding (MoU) and subsequent agreements (AoU, AoA) related to a real estate redevelopment project in Mumbai. The project involved the Corporate Debtor, Thakkars (partners), and Investors (Respondents 1-3). The Investors provided funds for the project, but due to disputes and lack of progress, the project stalled. The core issue revolves around the repayment of the investment and whether the Section 7
…In 2010, Atul Projects India Private Limited (Corporate Debtor) planned a redevelopment project in Mumbai. A Memorandum of Understanding (MoU) was signed on 2010-05-16 with the Owners, Confirming Parties, and the Corporate Debtor. The Corporate Debtor was to pay ₹9.40 Crores to the Owners. Thakkars (Deepak Vinod Thakkar and Prashant Vinod Thakkar) entered into an Articles of Understanding (AoU) with the Corporate Debtor, agreeing to jointly redevelop the project. The Thakkars were to get an investment of ₹6 Crores. An Articles of Agreement (AoA) was signed on 2010-05-16 between the Thakkars and Manish Pardasani, Savinder Singh Lamba, and Kulbir Singh Rekhi (Respondents No. 1 to 3), the Investors. The Investors would provide ₹6 Crores to the Thakkars, and in return,
…Memorandum of Understanding (MoU), Articles…
The Corporate Debtor…