The Appellant, RCC E-Construct Pvt. Ltd., challenged an order dated 28.04.2025 passed by the NCLT, Division Bench-1, Chennai, in IA(IBC)/660/(CHE)/2025. The Appellant sought a recall of an order passed on merits on 24.03.2025, invoking Rule 11 of the NCLT Rules.
The Corporate Debtor, M/s. P Dot G Constructions Pvt Ltd, was placed under insolvency proceedings by an order dated 13.07.2018 in CP/193(IB)/CB/2018.
RCC E-Construct Pvt Ltd, the Appellant, claimed to be the Successful Resolution Applicant and contended that the resolution plan was approved by the NCLT.
Six homebuyers filed an application seeking execution of the sale deed of their respective units of the real estate developed by the Corporate Debtor.
The NCLT disposed of the homebuyers' application on 24.03.2025, directing the Appellant to act as per the approved Resolution Plan.
The Appellant filed a recall application on 10.04.2025, seeking to recall the order dated 24.03.2025.
…Sign in to view the parties.
M/s. P Dot G Constructions Pvt Ltd was placed…
The Tribunal approved the Resolution Plan for…
The Appellant, RCC E-Construct Pvt. Ltd., challenged an order dated 28.04.2025 passed by the NCLT, Division Bench-1, Chennai, in IA(IBC)/660/(CHE)/2025. The Appellant sought a recall of an order passed on merits on 24.03.2025, invoking Rule 11 of the NCLT Rules.
The Corporate Debtor, M/s. P Dot G Constructions Pvt Ltd, was placed under insolvency proceedings by an order dated 13.07.2018 in CP/193(IB)/CB/2018.
RCC E-Construct Pvt Ltd, the Appellant, claimed to be the Successful Resolution Applicant and contended that the resolution plan was approved by the NCLT.
Six homebuyers filed an application seeking execution of the sale deed of their respective units of the real estate developed by the Corporate Debtor.
The NCLT disposed of the homebuyers' application on 24.03.2025, directing the Appellant to act as per the approved Resolution Plan.
The Appellant filed a recall application on 10.04.2025, seeking to recall the order dated 24.03.2025.
…M/s. P Dot G Constructions Pvt Ltd was placed…
The Tribunal approved the Resolution Plan for…