The petitioner, M/S ANGLE INFRASTRUCTURE PVT. LTD., filed a petition seeking restraint against the Directorate of Enforcement from taking coercive steps, including attachment of property, in relation to ECIR No. GNZO/11/2025. The petitioner is undergoing Corporate Insolvency Resolution Process (CIRP).
M/S ANGLE INFRASTRUCTURE PVT. LTD. is a company engaged in the development of Real Estate Projects in Delhi-NCR region.
In 2012-13, the petitioner launched a residential project at Sector-70, Gurugram comprising of 510 units.
The petitioner failed to deliver the project within stipulated timelines.
Homebuyers formed Krissh Florence Estate Buyers Welfare Association (KFEBWA) in 2015 to monitor the project's progress.
KFEBWA filed a petition under Section 7 of the Insolvency and Bankruptcy Code, 2016 before the NCLT due to non-delivery of flats.
The NCLT initiated Corporate Insolvency Resolution Process (CIRP) vide order dated 19.12.2024.
The Directorate of Enforcement (ED) initiated proceedings based on FIR No.48/2023, registered on 12.06.2023.
…Sign in to view the parties.
The petitioner launched…
Homebuyers formed…
Sign in to view related legal provisions.
The petitioner, M/S ANGLE INFRASTRUCTURE PVT. LTD., filed a petition seeking restraint against the Directorate of Enforcement from taking coercive steps, including attachment of property, in relation to ECIR No. GNZO/11/2025. The petitioner is undergoing Corporate Insolvency Resolution Process (CIRP).
M/S ANGLE INFRASTRUCTURE PVT. LTD. is a company engaged in the development of Real Estate Projects in Delhi-NCR region.
In 2012-13, the petitioner launched a residential project at Sector-70, Gurugram comprising of 510 units.
The petitioner failed to deliver the project within stipulated timelines.
Homebuyers formed Krissh Florence Estate Buyers Welfare Association (KFEBWA) in 2015 to monitor the project's progress.
KFEBWA filed a petition under Section 7 of the Insolvency and Bankruptcy Code, 2016 before the NCLT due to non-delivery of flats.
The NCLT initiated Corporate Insolvency Resolution Process (CIRP) vide order dated 19.12.2024.
The Directorate of Enforcement (ED) initiated proceedings based on FIR No.48/2023, registered on 12.06.2023.
…The petitioner launched…
Homebuyers formed…
Sign in to view related legal provisions.