# DHL Ecommerce (India) Private Limited vs. Future Supply Chain Solutions Limited

> NCLT judgment dated 13 Oct 2025. Citation: TCN-2025-NCLT-01504. The case pertains to an application filed by Mr. Rajan Rawat, the Resolution Professional of…

- **Court:** NCLT
- **Order date:** 13 Oct 2025
- **Citation:** TCN-2025-NCLT-01504
- **Category:** IBC
- **Source page:** https://caseease.in/cases/ibc/nclt-kolkata/dhl-ecommerce-india-private-limited-vs-future-supply-chain-solutions-limited-97358a61

## Summary

### Background

The case pertains to an application filed by Mr. Rajan Rawat, the Resolution Professional of Future Supply Chain Solutions Limited, under Section 30(6) of the Insolvency and Bankruptcy Code, 2016, seeking approval of the Resolution Plan submitted by Reliance Retail Ventures Limited.

## Facts

DHL Ecommerce (India) Private Limited filed an application under Section 9 of the Insolvency and Bankruptcy Code, 2016.

The Tribunal admitted Future Supply Chain Solutions Limited into Corporate Insolvency Resolution Process (CIRP) on 05.01.2023.

Mr. Rajan Rawat was appointed as the Interim Resolution Professional (IRP).

The IRP made a public announcement on 21.01.2023, with the last date for submission of claims being 02.02.2023.

The Committee of Creditors (CoC) was constituted on 10.02.2023.

The first CoC meeting was held on 17.02.2023, wherein the IRP was appointed as the Resolution Professional (RP).

The CoC approved a fresh issuance of Form-G on 13.04.2023.

Reliance Retail Ventures Limited submitted a resolution plan that was left with the CoC.

…

## Issues and analysis

### Issue 1: Whether the Resolution Plan submitted by Reliance …

**Ratio:** The conditions/scenarios stated by the Resolution Applicant under the Resolution Plan qua

…

**Reasoning:** The Resolution Applicant clarified that in case the MIHAN Warehouse is not available for

…

**Interpretation:** The Tribunal interpreted the resolution plan to determine if the condition

…

**Application:** The Tribunal determined that the scenario's stipulated under the Resolution

…

## Parties

- **Judges:** LAKSHMI G…; Shri. Hariharan…
- **Appellants:** Rajan R…
- **Respondents:** Future Supply…
- **Other parties:** Corporate…; Approval of…; +6 more

## Timeline

- **2023-01-05 — Admission in…**: Tribunal admitted the Corporate Debtor into Corporate Insolvency Resolution Process…
- **2023-01-21 — Public Annou…**: The IRP made a public announcement in Form A under Regulation 6 of the Insolvency and…

---