### Background

The case involves M/s. Jakson Engineers Limited as the applicant/petitioner and M/s. UM Green Lighting Pvt. Ltd. as the respondent. The matter is under Section 9 of the IBC, 2016. The order pertains to IA-1816/2023.

## Facts

M/s. Jakson Engineers Limited filed an application/petition against M/s. UM Green Lighting Pvt. Ltd. under Section 9 of the IBC, 2016. The specific details of the dispute between the parties are not explicitly stated in the order. The IBBI did not appear, nor did they file any report. The court issued a fresh notice to IBBI to look into the matter based on a previous order dated 10.04.2023. The Court Officer was directed to send copies of the orders to IBBI. The case was listed for further hearing on 05.06.2023. The absence of IBBI's appearance and report is a key fact that prompted the court's action.

## Issues and analysis

### Issue 1: Whether a fresh notice should be issued to IBBI to look into the matter in terms of the order dated …

**Ratio:** The court has the authority to direct regulatory bodies like IBBI to provide input and

…

**Reasoning:** The IBBI's absence and failure to file a report necessitated the issuance of a fresh

…

**Interpretation:** This demonstrates the court's proactive approach in seeking input from relevant

…

**Application:** Given IBBI's non-appearance and lack of a report, the court applied its

…

## Parties

- **Judges:** SHRI. ASHOK KUMAR…; SHRI. L. N.…
- **Appellants:** M/s. Jakson…
- **Respondents:** M/s. UM Green…; M/S UM GREEN…

## Timeline

- **2023-04-10 — Previous Ord…**: Reference to a previous order dated…
- **2023-05-04 — Order Del…**: Order delivered by the…

---

This is a preview. The full structured summary, issues, precedents and source judgment are available on CaseEase - Legal Intelligence Simplified: https://caseease.in/cases/ibc/nclt-division-bench-court-i-chenn/um-green-lighting-pvt-ltd-26e0bcff