### Background

The application was filed by the Interim Resolution Professional (IRP) seeking withdrawal of the petition due to a settlement between the Operational Creditor and the Corporate Debtor under Section 12A of the I&B Code, 2016. The IRP confirmed compliance with the provisions of the I&B Code, 2016, including paper publications to invite claims from creditors. No claims were received following the publication.

## Facts

Shri S Sivakumar (Sri Kumaran Steels India Pvt Ltd) filed a petition CP/1165/(IB)/2018. The Interim Resolution Professional (IRP) filed an application MA/1047/2019 seeking withdrawal of the petition due to a settlement between the Operational Creditor and the Corporate Debtor. The settlement was reached under Section 12A of the I&B Code, 2016. The IRP initiated the CIRP and complied with the provisions of the I&B Code, 2016, by publishing notices to invite claims from creditors. The publication was effected in 'Indian Express' (English) and 'Dina Mani' (vernacular) on 2019-09-19, with a last date for claim receipt of 2019-10-03. No claims were received from any creditors of the Corporate Debtor following the publication. The CIRP cost, including the IRP's fees,

…

## Issues and analysis

### Issue 1: Whether the application for withdrawal of the petition should be allowed based on the settlement …

**Ratio:** Section 12A of the I&B Code, 2016, allows for the withdrawal of a CIRP application if

…

**Reasoning:** The tribunal considered the provisions of Section 12A of the I&B Code, 2016, which

…

**Interpretation:** Section 12A provides a mechanism for parties to resolve disputes outside the

…

**Application:** Since a settlement was reached between the Operational Creditor and the

…

## Parties

- **Judges:** SHRIR VARAD…; SHRI. ANIL…
- **Appellants:** S SIVAK…
- **Respondents:** KUMARAN STEELS…

## Timeline

- **2018-01-01 — Petition…**: CP/1165/(IB)/2018 filed by Shri S…
- **2019-09-19 — Publication o…**: Publication of notice in 'Indian Express' and…

## Legal provisions