# In the matter of Sintex Industries Ltd. C.P. (IB) No. 666-NCLT-AHM-2019

> NCLT judgment dated 2021-01-05. Citation: TCN-2021-NCLT-03397. The case pertains to C.P.(I.B) No. 666/NCLT/AHM/2019 before the National Company Law Tribunal…

- **Court:** NCLT
- **Order date:** 5 Jan 2021
- **Citation:** TCN-2021-NCLT-03397
- **Category:** IBC
- **Source page:** https://caseease.in/cases/ibc/nclt-chandigarh/sintex-industries-ltd-cp-ib-no-666-nclt-ahm-2019-5942e6f1

## Summary

### Background

The case pertains to C.P.(I.B) No. 666/NCLT/AHM/2019 before the National Company Law Tribunal (NCLT), Ahmedabad Bench. The matter involves Aum Construction V/s Sintex Industries Ltd. The advocate for the Petitioner was last present on 2020-01-27. Subsequently, the matter was fixed on multiple dates: 2020-02-28, 2020-06-03, 2020-06-26, 2020-08-10, 2020-09-11, and 2020-11-02. However, the advocate for the Petitioner remained absent on all these dates.

## Facts

The case involves Aum Construction as the Petitioner and Sintex Industries Ltd as the Respondent. The advocate representing Aum Construction last appeared before the NCLT Ahmedabad Bench on 2020-01-27. The matter was subsequently listed on 2020-02-28, 2020-06-03, 2020-06-26, 2020-08-10, 2020-09-11, and 2020-11-02. However, the advocate for Aum Construction was absent on all these dates. On 2021-01-05, the date of the order, no one appeared on behalf of the Petitioner. This consistent absence led the NCLT to dismiss the matter for non-prosecution.

## Issues and analysis

### Issue 1: Whether the matter should be dismissed due to the …

**Ratio:** A case can be dismissed for non-prosecution if the party or their representative fails to

…

**Reasoning:** The court reasoned that the advocate for the Petitioner had been consistently absent on

…

**Interpretation:** The interpretation of the law allows the court to dismiss a case if the

…

**Application:** In this specific case, the advocate's repeated absence on several fixed dates

…

## Parties

- **Judges:** Manorama…; Chockalingam…
- **Appellants:** Aum Constr…
- **Respondents:** Sintex Industries…

## Timeline

- **2020-01-27 — Last Appearance of…**: The advocate for the Petitioner, Aum…
- **2020-02-28 — Hearing…**: Hearing scheduled;…

## Legal provisions

- [Insolvency and Bankruptcy Code, 2016, Section 9 — Application for initiation of corporate insolvency…](https://caseease.in/legal-provisions/insolvency-and-bankruptcy-code-2016/section-9)

---