# In the matter of Pebble Glossy Metals Pvt. Ltd. IA-5639-ND-2021 in 
IB-3084-ND-2019

> NCLT judgment dated 2021-12-13. Citation: TCN-2021-NCLT-00198. This is an application for the correction of a clerical error regarding the name of the Interim…

- **Court:** NCLT
- **Order date:** 13 Dec 2021
- **Citation:** TCN-2021-NCLT-00198
- **Category:** IBC
- **Source page:** https://caseease.in/cases/ibc/nclt-chandigarh/pebble-glossy-metals-pvt-ltd-ia-5639-nd-2021-in-ib-3084-nd-2019-731bbcbf

## Summary

### Background

This is an application for the correction of a clerical error regarding the name of the Interim Resolution Professional (IRP). Initially, Mr. Ashish Singh was appointed as the IRP, but later, Mr. Sudhanshu Gupta was chosen with consent. A mistake occurred inadvertently during the appointment process.

## Facts

The case involves an application to correct a clerical error concerning the name of the Interim Resolution Professional (IRP). Initially, Mr. Ashish Singh was appointed as IRP. Subsequently, Mr. Sudhanshu Gupta was chosen with consent. Due to an inadvertent mistake, the incorrect name was recorded. The application seeks to rectify this error, ensuring Mr. Sudhanshu Gupta is correctly identified as the IRP. Mr. Sudhanshu Gupta's office address is 311, Aggarwal Chamber-2, Plot No. 30, 31, Veer Savarkar Block, Opp. Metro Pillar No. 58, Shakarpur, East Delhi-110092, with email ID sg_1973@rediffmail.com and Regn. No. IBBI/IPA-002/IP-N00216/2017-18/10668.

## Issues and analysis

### Issue 1: Whether the clerical error regarding …

**Ratio:** Clerical errors can be corrected to reflect the true intention and agreement of the

…

**Reasoning:** The court reasoned that a mistake occurred inadvertently, and correcting it would align

…

**Interpretation:** This interpretation allows for the rectification of minor errors that do not

…

**Application:** The court applied this principle by allowing the correction of the IRP's name,

…

## Parties

- **Judges:** DHARMINDER…; Narender Kumar…
- **Appellants:** Neha…
- **Respondents:** Pebble Glossy…

## Timeline

- **2021-12-13 — Order Del…**: Order delivered on the application…
- **2021-12-17 — Order Si…**: Order signed by Dharminder…

---

This is a preview. The full structured summary, issues, precedents and source judgment are available on CaseEase - Legal Intelligence Simplified: https://caseease.in/cases/ibc/nclt-chandigarh/pebble-glossy-metals-pvt-ltd-ia-5639-nd-2021-in-ib-3084-nd-2019-731bbcbf