# In the matter of Jadeja Ravirajsinh Juvansinh vs. Nuvoco Vistas Corporation Ltd. & Ors.

> NCLAT judgment dated 2025-08-21. Citation: TCN-2025-NCLAT-00467. The Appellant, claiming to be an employee and authorized representative of employees of M/s.…

- **Court:** NCLAT
- **Order date:** 21 Aug 2025
- **Citation:** TCN-2025-NCLAT-00467
- **Category:** IBC
- **Source page:** https://caseease.in/cases/ibc/nclat-new-delhi/jadeja-ravirajsinh-juvansinh-vs-nuvoco-vistas-corporation-ltd-ors-096dae77

## Summary

### Background

The Appellant, claiming to be an employee and authorized representative of employees of M/s. Vadraj Cement Ltd., filed an appeal challenging the order dated 01.04.2025 approving the Resolution Plan of the Corporate Debtor, M/s Vadraj Cement Limited.

## Facts

The Corporate Insolvency Resolution Process (CIRP) against Vadraj Cement Ltd. commenced on 02.02.2024.

The Resolution Plan was approved by the Committee of Creditors (CoC) with 100% majority.

The Resolution Plan provided for a total amount towards provident fund of Rs.10,51,00,841/- and Rs.6,30,10,916/- for employee claims.

An email dated 24.04.2025 from the RP indicated that unpaid gratuity dues would be paid out of the Rs.6,30,10,916/-.

The Appellant argued that gratuity dues should be paid in addition to the Rs.6,30,10,916/-.

The Resolution Plan's Clause 13.1.2 stipulates that employee dues, including gratuity, are to be paid from Rs.6,30,10,916/-.

## Issues and analysis

### Issue 1: Whether the payment of unpaid gratuity dues has to be in addition to the payment proposed to the …

**Ratio:** The Resolution Plan's Clause 13.1.2 clearly provides that all employee dues, including

…

**Reasoning:** The Tribunal examined the relevant clauses of the Resolution Plan, particularly Clause

…

**Interpretation:** The Tribunal interpreted the Resolution Plan to mean that the payment of

…

**Application:** The Tribunal applied the clauses of the Resolution Plan to the facts of the

…

## Parties

- **Judges:** Ashok Bh…; Barun M…
- **Appellants:** Jadeja Ravirajsinh…
- **Respondents:** Vadraj Cement…; Nuvoco Vistas…
- **Other parties:** Employees of…; Pulkit…
- **Advocates:** Anju…; Hitesh S…; +12 more

## Timeline

- **2024-02-02 — Commencement…**: The Corporate Insolvency Resolution Process…
- **2024-02-03 — Public Annou…**: Public announcement was made, and claims…

---